During PI Planning, which statement is true about the activities of team breakouts?At team

During PI Planning, which statement is true about the activities of team breakouts?At team breakout #1, teams refine their backlogAt team breakout #1, teams finalize program risks, impediments, and dependenciesAt team breakout #2, teams establish a draft of their business objectivesAt team breakout #2, teams work to create their final plans