Calculate the variance for each of the projectactivities.
OptimisticTime Most-likelyTime PessimisticTime
Activity Estimate(weeks) Estimate (weeks) Estimate(weeks) Variance σ2
A 3 6 9
B 3 5 7
C 4 7 12
D 4 8 10
E 5 10 16
F 3 4 5
G 3 6 8
H 5 6 10
I 5 8 11
J 3 3 3