Activity Arrow Aoa Network Diagram Project Lettered F Represents Activity Shown Accompany Q30033850

.Here is an Activity on Arrow (AOA) network diagram for aproject. The lettered A through F represents an activity, as shownin the accompanying precedence diagram. The probabilistic time foreach activity is as follows Activi Time Activi Time 4-5-6 4-5-62-5-6 2-5-6 3-4-7 3-4-6 What is the expected time and standarddeviation of path A-C-D? What percentage will path A-C-D finishwithin 13 weeks? Here is an Activity on Arrow (AOA) network diagramfor a project. The lettered A through F represents a sub-project,as shown in the accompanying precedence diagram. The deterministictime for each activity is as follows Activi Time Activi Time 3 5 68 c 5 4 (1) Which path is the critical path? What is the expectedduration of the project? (2) What are the Earliest Start (ES) andEarliest Finish (EF) time, Latest Start (LS), Latest Finish (LF)and Slack time for each activity?