A. Assume a small four-week software enhancement is budgeted for$10,000. While reporting status during the third week, the projectmanager determines his team has only completed 50 percent of thework. Based on the project schedule, the team was supposed tocomplete 75 percent of the work during the third week. The projectmanager also noticed they had spent $9,000 to date on the project.calculate the CV, SV, CPI, SPI and EV interpreting your results?With the problem raised, critically evaluate how much money wouldbe needed to complete the project and the new estimate atcompletion (EAC) for the project.
B. Explain the stages and documentation required for aneffective integrated change control for a typical project.